Requirement Workflow
1. Objective
The requirement workflow ensures that software work begins only after the requirement is sufficiently complete, reviewed, approved, and assigned a specific version.
2. Requirement Lifecycle
Primary states:
DRAFT
↓
SUBMITTED
↓
UNDER_BA_REVIEW
↓
UNDER_PM_REVIEW
↓
UNDER_TECHNICAL_REVIEW
↓
UNDER_QA_REVIEW
↓
APPROVED
↓
IN_DEVELOPMENT
↓
IMPLEMENTED
↓
QA_VERIFIED
↓
BA_ACCEPTED
↓
RELEASED
Alternative states: CHANGES_REQUESTED, REJECTED, ON_HOLD, CANCELLED, SUPERSEDED
3. Requirement Creation
A Business Analyst creates a requirement in DRAFT status.
Mandatory information:
- Project, title, business objective, detailed description
- Actor or user role, main workflow
- Business rules, acceptance criteria
- Priority, author, creation date
Conditionally mandatory:
- UI references, integration details, dependencies
- Data migration requirements, security considerations
- Attachments, alternative workflows, out-of-scope items
4. Draft Editing
While in DRAFT:
- The author may edit it freely
- Assigned collaborators may comment
- Validation warnings may be displayed
- Draft changes are still recorded in history
5. Submission
When the BA submits the requirement:
- System validates required fields
- System checks Definition of Ready
- System assigns a review workflow
- Requirement becomes SUBMITTED
- Reviewers receive notifications
6. Review Process
BA Review
BA reviewer verifies:
- Business problem is clear
- Objective is measurable
- Workflows are complete and consistent
- Acceptance criteria are testable
PM Review
Project Manager verifies:
- Priority is clear and realistic
- Target release is achievable
- Dependencies are identified
- Scope boundaries are clear
Technical Review
Technical Lead verifies:
- Technical feasibility and architecture impact
- Integration and database impact
- Security impact and performance considerations
- Migration needs and development estimate readiness
QA Review
QA verifies:
- Acceptance criteria are testable
- Expected results are unambiguous
- Edge cases are identified
- Required test data is available
7. Approval
After all mandatory reviews pass:
- System assigns next version number (starting at 1.0)
- Requirement version becomes APPROVED
- Version is locked (immutable)
- Immutable snapshot is stored
- Approval records are stored
- Audit events are created
- Approved version becomes current source of truth
8. Immutability Rule
Critical: An approved requirement version cannot be edited through:
- User interface
- Public API
- Bulk update
- Administrator screen
Any change must create:
- A change request
- A new draft requirement version
- A recorded reason for change
- A version relationship to the approved version
9. Development Transition
The requirement may enter IN_DEVELOPMENT when:
- At least one task is linked
- Required approvals are complete
- No blocking clarification remains
- PM assigns the work to a sprint
10. Implementation and Release
- IMPLEMENTED: All mandatory linked tasks are DONE
- QA_VERIFIED: Required test cases executed and passed
- BA_ACCEPTED: BA confirms implementation satisfies the approved version
- RELEASED: Included in an approved release and deployed
11. Clarifications
A clarification may be raised at any point before release.
Clarification fields:
- Question, asked by, assigned to, due date
- Requirement version, response, resolution
- Decision status, confirmed by, confirmed date
A clarification becomes an official project decision only after confirmation by an authorized role.
12. Version Numbering
Recommended rules:
- 1.0: First approved version
- 1.1: Minor clarification with limited scope impact
- 2.0: Major workflow, rule, scope, or acceptance change
13. Workflow Audit
The system preserves:
- Previous and new status, changed by, changed date
- Review comment, approval/rejection reason
- Requirement snapshot, version identifier
- Related change request, trace ID